Newport News

From Jefferson Avenue in Newport News to Mercury Boulevard in Hampton, an existing HOV lane will be converted into an Express Lane in both directions. From Mercury Boulevard to LaSalle Avenue in Hampton, one Express Lane will be constructed in each direction. The total length of the project is 13.5 miles.

Major Work Items:

  • Two bridge replacements (EB/WB LaSalle Avenue)
  • One bridge rehabilitation (EB/WB Armistead Avenue)
  • One mile of EB and WB road widening
  • Overhead signage
  • Right of way acquisition
  • Tolling gantries
Project Cost: $156 million
Important Dates
  • Public Hearing
    • Virtual, Sept. 29, 5:30-7:30 p.m. Register Here
    • In-person, Sept. 30, 4-7 p.m. Y.H. Thomas Community Center
      1300 Thomas Street, Hampton, VA 23669
  • Advertisement: Summer 2023
  • Notice to Proceed: Summer 2023
  • Fixed Completion Date: Winter 2025
  • Draft Categorical Exclusion
  • Public Hearing Plans